title: "How do you carry out an industrial battery LCA? What does the Batteries Regulation require?"
description: "Industrial battery LCA above 2 kWh: Regulation 2023/1542 requires a carbon footprint declaration (CFB). €12,000-€25,000 excl. VAT, 6 months, plus verification."
canonical: https://projetcelsius.com/en/blog/industrial-battery-lca-how-to-start/
author: "Guillaume Pakula"
datePublished: 2026-04-06
dateModified: 2026-10-24
language: en
translationOf: https://projetcelsius.com/blog/acv-batterie-industrielle-par-ou-commencer/
---

# How do you carry out an industrial battery LCA? What does the Batteries Regulation require?

**Author**: Guillaume Pakula
**Published**: 2026-04-06
**Updated**: 2026-10-24
**Section**: Practical guide
**Canonical URL**: https://projetcelsius.com/en/blog/industrial-battery-lca-how-to-start/
**French original**: https://projetcelsius.com/blog/acv-batterie-industrielle-par-ou-commencer/
**Source**: Projet Celsius (https://projetcelsius.com/en/), a climate strategy consultancy of engineers and PhDs based in Paris and Marseille.

> [EU Regulation 2023/1542](https://projetcelsius.com/en/blog/eu-battery-regulation-2023-1542/) requires a **verified carbon footprint declaration** for every industrial battery above **2 kWh** placed on the European market. Without it, no CE marking and therefore no placing on the market. The deadline still depends on the delegated act setting the calculation method: the declaration will apply 18 months after it enters into force, **during 2028 at the earliest**. The project takes **6 months**, and accredited verification bodies are still scarce. This guide follows the steps of the project in order, so that you can start the declaration without losing time.

## Key takeaways

- **CFB rather than complete LCA**: €12k to €25k excl. VAT and 6 months, rather than about double the budget and 8 to 12 months.
- **You are the declarant** if you assemble in Europe: your cell supplier has no obligation.
- **Supplier collection = critical path**: 8 to 12 weeks for a usable dataset from an Asian manufacturer.
- **Deadline during 2028 at the earliest** for industrial batteries above 2 kWh: start the project in the second half of 2026.

Once the requirement applies, **during 2028 at the earliest**, no industrial battery above 2 kWh will be able to enter the European market without a **carbon footprint declaration verified by a third-party body**. Regulation [EU 2023/1542](https://projetcelsius.com/en/blog/eu-battery-regulation-2023-1542/) made this a condition of CE marking, alongside safety tests.

The sections below follow the steps of a declaration project and flag the mistakes that cost those who start without a safety net 3 to 6 months of delay.

## What does the EU Battery Regulation require?

Most manufacturers we support discover this requirement during a sales meeting: a client asks for the carbon declaration, the compliance manager looks into it and finds a Regulation with 117 articles and delegated acts arriving progressively. This first section sets out what is required, from whom and in what form.

The Regulation requires manufacturers and importers of industrial batteries above **2 kWh** to produce a **carbon footprint declaration** (Carbon Footprint of Batteries, or CFB). This quantified document states: over its entire life cycle, this battery emits X kilograms of CO₂ equivalent per kilowatt-hour delivered. It is a regulatory requirement, distinct from an audit or a voluntary label. Without this verified declaration, there is no CE marking and no placing on the European market.

The declaration follows a precise methodology developed by the [JRC](https://joint-research-centre.ec.europa.eu/) (the European Commission’s research centre), based on the **PEF** (Product Environmental Footprint) method. It must be verified by a **notified third-party body**.

### CFB vs complete LCA: what is the difference?

This is the most frequent and costly misunderstanding. The carbon footprint declaration is **not** a [complete life cycle assessment (LCA)](https://projetcelsius.com/en/blog/product-carbon-footprint-lca-pef-cfp/). The data to collect are largely the same, but the deliverable, budget and timetable differ considerably.

- The CFB, **the one the Regulation requires**, covers just 1 indicator (kgCO₂e/kWh), with a deliverable focused on regulatory compliance. It costs **€12,000 to €25,000 excl. VAT**, not including verification, and takes **6 months**.
- The **complete multi-indicator LCA** covers 16 impact categories (global warming, acidification, eutrophication, toxicity, etc.). It costs **about double** and takes **8 to 12 months**, for a broader deliverable that the Regulation does not require.
- A manufacturer that commissions a complete LCA when it needs a CFB risks **doubling its budget**, for a deliverable that goes beyond what the Regulation requires.

### Who must produce the declaration?

It is the economic operator placing the battery on the European market. If you assemble battery packs from cells purchased from a Chinese or Korean manufacturer (CATL, EVE Energy, BYD), **you** are the declarant, not your cell supplier. You must obtain its data, incorporate them into your calculation and produce the declaration. Many European assemblers have yet to grasp this, and discover along the way that their cell supplier has no obligation to make their lives easier.

> An assembler that buys its cells is the declarant itself, and its supplier has no obligation to make its life easier.

## Which calculation method must you follow?

The Regulation leaves no choice of method: the declaration must follow a precise framework set by the JRC, derived from PEF (Product Environmental Footprint). This framework imposes 3 things on you: a **standardised calculation scope** (cradle to end of life, excluding the use phase), a **result unit** (kgCO₂e per kWh delivered over the lifetime) and a **hierarchy of data sources**. In this hierarchy, primary data come first, and secondary data are used only as a justified fallback. The sub-sections below explain these 3 constraints in plain language, which the official documentation does not.

### Scope: cradle to end of life, without the use phase

The calculation covers 4 stages (Annex II of the Regulation): extraction and pre-processing of raw materials (lithium, cobalt, nickel, graphite), manufacturing, distribution, and then end of life and recycling. The use phase is excluded. End of life carries weight: when materials are recycled and avoid the production of virgin materials, the footprint falls. The Regulation sets progressive recovery targets:

- For **lithium**, the target is 50% by the end of 2027, then 80% by the end of 2031.
- For **cobalt, copper and nickel**, the target is 90% from the end of 2027.
- In the **end-of-life and recycling** stage, recovered materials reduce the final footprint, all the more so when the recycling scenario is ambitious.

### Functional unit: the kWh delivered

The result is expressed as **kgCO₂e per kWh of total energy delivered over the lifetime**, rather than "kg of CO₂ per battery". Cycle life therefore appears in the denominator. A battery lasting **6,000 cycles** has half the footprint per kWh delivered of an identical battery lasting only 3,000, even if their manufacture had exactly the same carbon cost. This is a structural advantage for batteries designed to last, and a measurable argument for thermal management systems (immersion cooling, optimised battery management system or BMS) that extend lifetime.

### Primary vs secondary data

The Regulation distinguishes between **primary data** (your own measurements and those of your suppliers) and **secondary data** (generic databases such as ecoinvent or EF 3.1). The rule is simple: everything under your direct control must be covered by primary data. For upstream processes, supplier data are the target. Generic databases are accepted only as a last resort, and every use must be justified in the declaration.

> The electricity mix in the country where cells are manufactured matters more than everything else, to the point that an NMC battery manufactured in Norway can outperform an LFP battery manufactured in China.

## Which data must you collect, and from whom?

Once the methodological framework is set, the focus shifts to a single question: **obtaining the data**. This is the stage at which the project starts in earnest, and where it falls behind. The delay comes from collection, because modelling remains relatively standard once the data are in hand. Here are the 4 workstreams in order of criticality.

### Raw materials and geographical origin

This is the most demanding and consequential workstream. For every battery component, you need the precise chemical composition and geographical origin. The electricity mix in the cell manufacturing country is the leading impact factor, and the differences are considerable: an NMC811 cell ranges from **27 kgCO₂e/kWh** in Norway to **155** in China (source: ScienceDirect, 2024). Median footprints are around **62 kgCO₂e/kWh** for LFP compared with **74** for NMC811, around 16% lower (source: Nature Communications, 2024). But an NMC battery manufactured in Scandinavia can have a lower footprint than an LFP produced in a coal-powered Chinese province.

- You need the **cell chemistry** (NMC, LFP or NCA) and the composition of its active materials (cathode, anode, electrolyte, separator).
- For the **current collectors, casing and BMS**, you need the materials and their geographical origin.
- The **cooling system** (liquid, air, immersion) also matters, because it affects manufacturing energy.
- The **geographical origin of each component** determines the electricity mix, and therefore the impact.

The problem is obtaining these data. We were supporting a French assembler of stationary storage batteries, with LFP cells purchased from 2 Chinese suppliers. The first responded in 9 weeks with an Excel file in Mandarin, without the geographical origin of the lithium. The second responded in 10 days with a complete file, but the scopes did not match between the two. Standardising the data took another 3 weeks. So allow **8 to 12 weeks** to obtain a usable dataset from an Asian supplier, and send the questionnaire with explicit instructions on the expected units and formats.

### Manufacturing data (factory)

- You need the **energy consumption** in kWh per battery produced, distinguishing the dry room, formation/ageing and assembly.
- **Production yield** matters, because every defective cell has consumed energy for nothing.
- For **manufacturing waste**, you need the quantities and treatment routes.
- Your **site’s electricity mix** is described by the power purchase agreement (PPA), the national grid and the renewable share.

These are mandatory primary data: sector averages are not enough for your own processes. These data are, however, under your control and rarely difficult to obtain if your meters are in place.

### Transport and logistics

Distances and modes of transport between every link: from extraction to the cell manufacturer, from the manufacturer to your factory, and from your factory to the client. This is rarely the dominant source (sea transport of a finished battery contributes far less than the electricity mix in the manufacturing country), but the Regulation requires specific data and the verification body will check them.

### End of life and recycling

There are 2 main recycling routes, with very different profiles:

- **Hydrometallurgy** recovers materials better, including lithium, but it is more expensive and its sector is still scaling up.
- **Pyrometallurgy** is more mature industrially, but it loses lithium in the slag.
- **Uncertainty remains high**, because the European sector is young and actual large-scale data are scarce. This is the part of the calculation where assumptions have the greatest influence on the final result.

## What is the regulatory timetable?

The timetable under Regulation 2023/1542 has already changed. In July 2025, the Council postponed the due diligence deadline from August 2025 to August 2027 (Regulation 2025/1561), mainly to give notified bodies time to become established. For rechargeable industrial batteries above 2 kWh, here are the key dates:

- In **February 2027**, the [digital product passport (DPP)](https://projetcelsius.com/en/blog/espr-dpp-timeline-who-is-affected/) is required.
- **18 months after the methodological delegated act**, which is still awaited (during 2028 at the earliest), the carbon footprint declaration verified by a third-party body becomes mandatory.
- **After that** come the carbon performance classes (A, B, C), to compare batteries with one another.
- In **February 2030**, a maximum carbon footprint threshold takes effect, and batteries above it are banned from the market.

With 6 months for a first declaration, 4 to 8 weeks for third-party verification and reasonable preparation time, a manufacturer that wants to be ready without rushing should start its project in the **second half of 2026** at the latest.

### Typical timetable for a CFB project

- **Month 1** is for scoping and launching the supplier questionnaires, without waiting until everything is scoped, because supplier collection is the critical path.
- **Months 2 to 4** are for collecting supplier data, with follow-ups after 15 and 30 days. You also need to identify a technical contact at each supplier (not the salesperson) and prepare substitution scenarios using secondary data.
- **Month 5** is devoted to modelling and sensitivity analyses on the critical parameters (electricity mix, cathode chemistry, end of life).
- **Month 6** is when verification by a notified third-party body takes place.
- **For a second product** with the same value chain, divide this timetable by 2, since the model and contacts are already in place.

## Which mistakes can cost 6 months of delay?

We see these 3 mistakes recur consistently among manufacturers who start without support. Each can cost 3 to 6 months of delay or tens of thousands of euros.

- The first mistake is **underestimating supplier collection**, which is a matter of response time as well as of the quality of the data received. Formats are not standardised, and geographical traceability concepts are not always understood in the same way. The right contact (the factory’s technical manager, not the salesperson) is not always identified. Send your questionnaires from month 1, be explicit about the expected units and allow **8 to 12 weeks**.
- The second is **commissioning a complete LCA instead of a CFB**, when the Regulation requires a CFB. The confusion can double the budget and the timetable (from 6 to 12 months). Check what your provider is proposing in practice.
- The third is **failing to plan for third-party verification**, which takes **4 to 8 weeks**, while notified bodies for batteries are still few in number in Europe in 2026. Verification slots are booked 2 to 3 months in advance, without waiting for the model to be finalised.

## How does third-party verification work?

Verification is not a formality. The notified third-party body checks methodological compliance, primary data traceability, consistency of assumptions and justification of secondary data. The carbon footprint declaration forms part of the CE compliance file, alongside safety certifications.

In practice, here is what the body will request:

- **Modelling files**, meaning the complete model with all assumptions
- Completed and dated **supplier questionnaires**
- **Evidence of geographical origin** of raw materials (certificates, invoices, supplier declarations)
- **Documentation of methodological choices**, which explains why this scope and why a given secondary datum rather than a primary one
- **Sensitivity analyses**, which show how the result varies when the critical assumptions change

If your supplier data are incomplete or poorly documented, this is where things get stuck. Booking a slot **2 to 3 months** before your preferred date is prudent: notified bodies competent in industrial batteries are still becoming established in 2026.

## Where should you start with your carbon footprint declaration?

You are probably in one of these 2 situations: either you have not started yet and are looking for where to begin, or you have started and wonder whether you are on the right track. Whichever of the 2 applies, here is the sequence to follow.

**What can be done in-house**: collecting factory data (consumption, yield, your site’s electricity mix), regulatory scoping, identifying technical contacts at your suppliers and following up questionnaires. These workstreams are under your direct control and require no specialist PEF expertise. **What requires external support**: modelling itself (command of the PEF framework, scope selection, qualification of secondary data, sensitivity analyses), technical discussions with the notified body and critical review of responses from Asian suppliers. For a corporate social responsibility (CSR) team that has never carried out an LCA, learning the PEF method requires **2 to 3 weeks** full-time before producing the first line of the model. This is the most frequent blind spot when deciding to bring the work in-house without measuring the investment.

### Step 1 - Clarify the need: CFB or complete LCA

If the only objective is compliance with Regulation 2023/1542, you need a carbon footprint declaration (CFB). If you also aim for [product eco-design](https://projetcelsius.com/en/blog/first-product-lca-steps-cost-mistakes/) or multicriteria marketing communication, a [complete LCA](https://projetcelsius.com/en/blog/lca-vs-carbon-footprint/) can be justified, but the budget and timetable double.

### Step 2 - Send supplier questionnaires

This is the critical path. The questionnaires cover the exact cathode chemistry, the factory’s electricity mix and the geographical origin of the active materials. Be explicit about the expected units (kWh/battery, kgCO₂e/kWh of cell, percentage) and the response format. Do not wait until every methodological detail is scoped before sending the first questionnaires.

### Step 3 - Gather factory data

Energy consumption by process step, production yield and the site’s electricity mix are data you already have (or should have). If your meters are not in place, now is the time to install them.

### Step 4 - Book third-party verification

As soon as the project starts, identify a notified body and book a slot 2 to 3 months before your target date. Slots are scarce in 2026, and will be scarcer still in 2027.

## Key takeaways

The battery carbon footprint declaration is a market requirement: **without it, no CE marking and no placing on the European market**. The deadline for industrial batteries above 2 kWh will fall 18 months after the methodological delegated act, which is still awaited, meaning **during 2028 at the earliest**. A complete project takes 6 months to carry out, plus 4 to 8 weeks of third-party verification.

The method to ask your provider for is a **CFB** (€12k to €25k excl. VAT, 6 months), because the Regulation does not require a complete multi-indicator LCA, which costs about double and takes 8 to 12 months. The critical path is **collecting supplier data**, never modelling. Allow 8 to 12 weeks to obtain a usable dataset from an Asian cell manufacturer, and speak to the factory’s technical manager, not the salesperson.

Finally, the [electricity mix in the cell manufacturing country](https://projetcelsius.com/en/blog/lithium-ion-battery-carbon-footprint/) matters more than everything else: it is the variable that allows a Norwegian NMC to outperform a Chinese LFP. A manufacturer that wants to be ready without rushing must start its project in the **second half of 2026** at the latest, without waiting for publication of the delegated act.

> **Need support?** Do you manufacture or assemble industrial batteries and need to produce your carbon footprint declaration under Regulation 2023/1542? We support manufacturers and assemblers from supplier data collection to third-party verification. An initial 15-minute discussion to scope your project: [contact us](https://projetcelsius.com/en/contact/).

## Frequently asked questions

## Frequently asked questions

### How much does a battery carbon footprint declaration cost?

Between €12,000 and €25,000 excl. VAT for a standard CFB for one product, including data collection, modelling and support with third-party verification. A complete multi-indicator LCA costs about double (see our [LCA cost guide](https://projetcelsius.com/en/blog/lca-cost/)). For a second product with the same value chain, the cost is roughly divided by 2. [Public funding](https://projetcelsius.com/en/blog/climate-transition-funding-carbon-footprint-lca/) is available for industrial SMEs and mid-cap companies (ETI in French).

### What are the penalties if the declaration is not ready on time?

Without a verified carbon footprint declaration, the battery cannot obtain CE marking and therefore cannot be placed on the European market. This is first and foremost a commercial block, on top of which come the penalties set by each Member State (Article 93): your clients simply cannot buy your product any more.

### Does the declaration cover every batch or a battery model?

A battery model (a product reference), rather than every batch. But if you change cell supplier, chemistry or manufacturing site, you must recalculate because the input data have changed.

### My cell supplier refuses to share its data: what can I do?

This is common. The Regulation constrains only the declarant, rather than the supplier. Options: negotiate an NDA governing data sharing, use secondary data with a justification (penalising the score), or switch to a cooperative supplier. This is an increasingly important commercial differentiator for cell manufacturers.

### Can you use data from a competitor or a benchmark?

No. Accepted secondary data come from recognised databases (ecoinvent, EF 3.1), rather than a competitor. Every secondary datum must be justified, and the verification body will check the source’s relevance.

### What is the difference between the CFB and the digital product passport (DPP)?

The DPP is the digital medium that holds the product information (including the CFB). The CFB is the carbon footprint calculation itself. The DPP is required from February 2027, the CFB 18 months after the delegated act setting its method, meaning during 2028 at the earliest. Our [digital product passport guide](https://projetcelsius.com/en/blog/digital-product-passport-explained/) covers this in detail.

### What life cycle scope applies to a battery LCA?

For the carbon footprint declaration required under Regulation 2023/1542, the scope runs from raw material extraction (lithium, cobalt, nickel, graphite) through manufacturing and distribution to end of life and recycling; the use phase is excluded (Annex II). Recycled materials avoid virgin material production and reduce the final footprint. The result is expressed in kgCO2e per kWh delivered over the battery’s lifetime, which favours batteries designed to last.

### Which primary data should you request from cell suppliers?

Prioritise the exact cell chemistry (NMC, LFP or NCA) with the composition of active materials (cathode, anode, electrolyte, separator), the manufacturing factory’s electricity mix and the geographical origin of materials. The electricity mix in the manufacturing country is the leading impact factor: an NMC811 cell ranges from 27 kgCO2e/kWh in Norway to 155 in China. Specify the expected units (kWh per battery, kgCO2e per kWh of cell, shares in %) and contact the factory’s technical manager rather than the salesperson. Allow 8 to 12 weeks to obtain a usable dataset from an Asian supplier.

### How long does a battery LCA take?

Allow around 6 months for a first carbon footprint declaration (CFB), plus 4 to 8 weeks of verification by a third-party body. The first month covers scoping and sending supplier questionnaires, months 2 to 4 cover collection, which is the critical path, and month 5 covers modelling and sensitivity analyses. A complete multi-indicator LCA takes 8 to 12 months instead. For a 2nd product with the same value chain, timeframes are roughly divided by 2. To be ready on time, the project must start no later than the second half of 2026.

### Is the EU battery carbon footprint threshold already in force?

No, not for rechargeable industrial batteries above 2 kWh. For these, Regulation 2023/1542 provides for a gradual rollout, starting with the digital product passport (DPP), required in February 2027. Next comes the third-party-verified carbon footprint declaration, 18 months after the methodological delegated act, meaning during 2028 at the earliest, followed by the carbon performance classes (A, B, C). The maximum carbon footprint threshold arrives in February 2030 at the earliest: batteries exceeding it will be banned from the market. This timetable has already changed and depends on delegated acts, hence the value of starting data collection now.