title: "France’s RE2020: what does the 2028 carbon threshold change?\nWhich permits are affected?"
description: "RE2020: for permits submitted from 1 January 2028, Ic construction falls to 580 kgCO2e/m² for apartment buildings from 650, and to 710 for offices."
canonical: https://projetcelsius.com/en/blog/re2020-2028-thresholds/
author: "Sébastien Pierfederici"
datePublished: 2026-09-28
dateModified: 2026-09-28
language: en
translationOf: https://projetcelsius.com/blog/re2020-seuil-2028/
---

# France’s RE2020: what does the 2028 carbon threshold change? Which permits are affected?

**Author**: Sébastien Pierfederici
**Published**: 2026-09-28
**Section**: Regulation
**Canonical URL**: https://projetcelsius.com/en/blog/re2020-2028-thresholds/
**French original**: https://projetcelsius.com/blog/re2020-seuil-2028/
**Source**: Projet Celsius (https://projetcelsius.com/en/), a climate strategy consultancy of engineers and PhDs based in Paris and Marseille.

> For permits submitted from 1 January 2028, [RE2020](https://projetcelsius.com/en/blog/new-building-carbon-footprint-re2020/), France’s environmental regulation for new buildings, lowers **the Ic construction ceiling by 10 to 18%** depending on use, except for high-rise buildings. This tier remains in place: only these buildings obtained a relaxation in 2026. Buildings completed since 2022 are far from the new ceiling: **17% of apartment buildings** would already pass. The reduction is achieved first **through the structure and the quality of product data**, with foundations neutralised above a baseline.

## Key takeaways

- **Every permit submitted from 1 January 2028** falls under the new RE2020 carbon threshold.
- **Ceilings 10 to 18% lower**, including 580 kgCO2e/m² for apartment buildings.
- **Default data become a penalty in 2028**, particularly substantial for offices.
- For apartment buildings, **structure is the only work package** whose gap covers the required reduction.

A housing development whose outline design starts this autumn has a good chance of submitting its building permit in 2028, and will be assessed against RE2020’s third tier. For every permit application submitted from **1 January 2028**, the **construction carbon impact** ceiling falls by **10 to 18% depending on use**. It falls to **580 kgCO2e/m² for apartment buildings** from 650, to 475 for detached houses from 530 and to **710 for offices** from 810.

The timetable has not changed: the French decree of 18 March 2026, issued following Robin Rivaton’s RE2020 evaluation report, left the 2028 thresholds intact, **except for high-rise buildings**. However, summer 2026 brought 2 developments. The RE2020 observatory released its data, which we used to measure **the gap between completed buildings and the 2028 tier**. The decree of 12 September then confirmed **the end of gas in new homes** from 2027 permits.

## What does RE2020’s 2028 threshold measure?

RE2020 sets minimum outcomes for every new building on energy (bioclimatic demand Bbio, consumption Cep and Cep,nr), summer comfort, measured in degree-hours of discomfort, and carbon. **The 2025, 2028 and 2031 tiers apply to the 2 carbon indicators**, with Ic énergie ending in 2028. Energy and summer comfort requirements remain stable, apart from a few adjustments, including the Bbio adjustment for offices of more than 500 m².

### 2 carbon ceilings, calculated over 50 years

**Ic construction** measures the climate impact of building components and the construction site: product manufacture, transport, installation, maintenance, replacements and end of life, over a **50-year reference period**. **Ic énergie** measures energy consumption’s impact over the same duration. The 2 are expressed in **kgCO2e per m² of reference floor area**, habitable floor area for housing and usable floor area for other uses.

Calculation follows a **simplified dynamic life cycle assessment**: the later an emission occurs in the building’s life, the less weight it carries, and carbon stored for 50 years in bio-based materials is taken into account. Data come from FDES (the French format of environmental product declaration for construction products) and, for equipment, Product Environmental Profiles (PEP) or, failing these, from **default environmental data**, a point that becomes decisive in 2028. Our [guide to reading FDES for RE2020 calculations](https://projetcelsius.com/en/blog/how-to-read-fdes-re2020/) details their treatment in software.

### An average threshold, adjusted project by project

Published values are **average thresholds**, valid for a typical building. A project’s legally binding ceiling is obtained by applying **adjustments**. These depend in particular on dwelling and building size, climate zone (+30 kgCO2e/m² for housing in zone H2d or H3 below 400 m altitude), converted lofts, ceiling height and balconies. A further 4 corrections relate to foundations, roads, photovoltaics and the use of default data.

For completed apartment buildings recorded by the observatory, with permits mainly submitted in 2022 and 2023, **the adjusted ceiling reaches a median of 754 kgCO2e/m²** for an average threshold of 740. Adjustments move a typical project’s target little and matter mainly for projects with a large underground car park or very small dwellings.

## Ceilings 10 to 18% lower depending on use

The 2028 tier applies to all uses subject to RE2020, with varying intensity. **The reduction required is greater for the uses that entered the regulations in May 2026** than for housing, offices and education, which are at their third tier.

### Housing, offices, education: the third of 4 tiers

For the 4 original uses, the average Ic construction threshold falls from **530 to 475 kgCO2e/m²** for detached houses and from **650 to 580** for apartment buildings. It falls from **810 to 710** for offices and from 770 to 680 for primary and secondary education. The reduction required represents **55 to 100 kgCO2e/m²**, or 10 to 12% of the ceiling. Compared with 2022, the 2028 ceiling is 22% lower for apartment buildings and 28% lower for offices, and the final tier, in 2031, will reduce them to **490 and 600 kgCO2e/m²** respectively.

### Hotels, shops, healthcare: a first tier 20 months after entry

The 13 uses that have been subject to RE2020 since **1 May 2026** under [Decree No 2026-16](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000053378848) (hotels, restaurants, shops, nurseries, universities, libraries, healthcare, sport, industry and craft activities, airport terminals…) face their first tightening in 2028. It is greater than for the original uses, at **14 to 18%**. A hotel falls from 820 to 680 kgCO2e/m², a shop or restaurant from 800 to 670, an industrial building from 840 to 695 and a healthcare establishment from 880 to 760.

Operators already measuring the footprint of their [hotels](https://projetcelsius.com/en/blog/hotel-carbon-footprint/), [hospitals](https://projetcelsius.com/en/blog/hospital-carbon-footprint/), [universities](https://projetcelsius.com/en/blog/university-carbon-footprint/) or [industrial sites](https://projetcelsius.com/en/blog/industrial-site-carbon-footprint/) find in Ic construction an approach close to the **capital goods category** of their Bilan Carbone® (the French carbon accounting method), calculated here building by building over 50 years.

### High-rise buildings: the only relaxed tier

[Decree No 2026-200 of 18 March 2026](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000053703809) applies to permits submitted since 1 July 2026. It adapts the thresholds for **high-rise buildings** (top floor more than 50 m high for housing, more than 28 m for other uses). The French ministry considers these thresholds too difficult for such buildings to meet, particularly given their fire safety constraints. For them, the 2028 threshold is set at **95% of the 2025 threshold**, or 617.5 kgCO2e/m² for a residential tower instead of 580, then at 95% of that value in 2031. For these buildings, the adjustment that lowers the ceiling for large buildings is also neutralised or reduced.

For housing, the same decree stops counting the carbon of balconies above a certain area and of ceiling heights above 2.5 m. It also grants **25 kgCO2e/m²** to buildings connected to a designated district heating network that install [air conditioning](https://projetcelsius.com/en/blog/air-conditioning-environmental-impact/), **without changing the other 2028 average thresholds**.

Like any threshold set by decree, this timetable remains amendable by the government, a risk examined in our article on [environmental obligations exposed to the 2027 presidential election](https://projetcelsius.com/en/blog/france-2027-election-environmental-obligations/). **The ministry has published no draft legislation to that effect**: as recently as 3 September 2026, it presented publication of observatory data as a way to prepare for the next regulatory milestones.

> As at 28 September 2026, no legislation postpones RE2020’s 2028 tier, and only high-rise buildings have obtained a relaxed threshold, set at 95% of the 2025 value.

## What does the 2028 tier change for heating?

For energy, 2028 is also the final Ic énergie tier, but **ceilings for most uses have already been at their final level** since 2025. The reduction primarily affects buildings connected to district heating, and gas leaves new housing through separate legislation from 2027.

### District heating: ceilings align on 1 January 2028

In housing and education, a building connected to an urban district heating network currently benefits from a higher Ic énergie ceiling. If the network is **designated**, every building even retains the 2022 values for a permit submitted before 31 December 2027: **560 kgCO2e/m² for apartment buildings**, against 260 without a network. From 2028, ceilings for the 4 original uses align, **with or without a network**: 260 for apartment buildings, 160 for detached houses, 200 for offices, 140 for education. For uses entering in 2026, only the designated-network exemption disappears.

Among completed apartment buildings connected to district heating recorded by the observatory, **35% would exceed the 2028 Ic énergie ceiling**, against 2% of those heated by heat pumps. For a project connected to a designated network whose permit slips into 2028, **the network’s carbon content** should be checked before designing plant rooms.

### Gas leaves new housing from 2027 permits

RE2020 has already effectively ruled out gas boilers as the main heating system, since 2022 for detached houses and since 2025 for apartment buildings, but allows supplementary heating. [Decree No 2026-863 of 12 September 2026](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000054834875) goes further. In a new building, **every heating, cooling or domestic hot water appliance** will have to use energy emitting less than **79 gCO2e/kWh**, the threshold adopted for electricity, which excludes gas even for supplementary use.

The obligation applies to permits and prior declarations submitted from **1 January 2027 for housing**, **1 January 2028 for buildings belonging to public bodies** and 1 January 2030 for others. District heating connections and emergency equipment are exempt. The choice of a heat pump will have to take account of the [European refrigerant timetable](https://projetcelsius.com/en/blog/f-gas-regulation-2027-bans/), and heating gas will enter the [second European carbon market in 2028](https://projetcelsius.com/en/blog/ets2-carbon-price-fuel-heating/).

## Does a permit submitted in late 2027 still fall under the 2025 threshold?

Yes: **the year of submission of the building permit application**, or prior declaration, sets the applicable tier, regardless of construction or completion date. A permit submitted on 31 December 2027 remains assessed against the 2025 thresholds even if the building is completed in 2030; submitted on 3 January 2028, it falls under the new tier.

Compliance is checked 2 times: through a **certificate attached to the permit submission**, then a **certificate on completion of works**, based on an updated study that must remain below the submission year’s ceilings.

### Amending permit, new permit: 2 distinct situations

An **amending permit** requires no new RE2020 certificate, according to the [ministry’s FAQ](https://rt-re-batiment.developpement-durable.gouv.fr/faq-re2020-035-un-permis-de-construire-modificatif-a610.html): the updated end-of-works study incorporates project changes. The FAQ does not specify the applicable tier, but this absence of a new certificate supports retaining the initial permit’s tier. A **new permit**, submitted after refusal, withdrawal or a redesigned programme, falls under the tier of its own submission year.

The practical risk affects developments designed to the 2025 threshold whose submission slips by a few weeks, for lack of a land agreement or a settled programme. **An apartment building outline design at 640 kgCO2e/m²** is compliant for a submission in December 2027 but no longer for a submission in January 2028, with the same adjustments.

### Housing faces 2 deadlines within 12 months

For a housing programme, the timetable stacks 2 reductions: permits submitted in 2027 must already dispense with gas, including supplementary use, and those submitted in 2028 must also meet the new carbon ceilings. For their other buildings, schools, offices or facilities, **public clients face the 2 deadlines on the same day**, 1 January 2028, while also having to incorporate an [environmental criterion in their procurement](https://projetcelsius.com/en/blog/public-procurement-environmental-criterion-how-to-respond/).

## Fewer than one in 5 completed apartment buildings would pass the 2028 threshold

Since summer 2026, the ministry has published **RE2020 observatory** data, drawn from regulatory certificates, on [data.gouv.fr](https://www.data.gouv.fr/datasets/opee-observatoire-des-performances-energetiques-et-environnementales-des-batiments-neufs), the French government’s open data portal. Our calculation starts from the extract as at 1 January 2026, covering **110,906 completed new buildings** with permits submitted between 2022 and 2025. It recalculates each building’s 2028 ceiling with its project-specific adjustments, excluding the balcony and ceiling height adjustments introduced in 2026.

### A median gap of 15 to 26% above the threshold

As built, **17% of apartment buildings**, 9% of detached houses and 21% of office buildings would already meet the 2028 ceiling. The median gap above the threshold reaches **+15% for apartment buildings**, or around 90 kgCO2e/m², +19% for detached houses and **+26% for offices**, where dispersion is greatest.

These buildings targeted the 2022 threshold. Nevertheless, the share of apartment buildings below the 2028 threshold is rising, from **16% for 2022 permits to 22% for 2024 permits**. Developments submitting in 2028 still start from current practice **around 90 kgCO2e/m² from the target**.

### Default data: a bonus until 2024, a penalty from 2028

The **Mided** coefficient adjusts the ceiling according to the contribution of default data and fixed values in the calculation, excluding foundations, roads and photovoltaics. This contribution is compared with a use-specific threshold (**250 kgCO2e/m² for apartment buildings**, 275 for offices, 300 for education, 370 for detached houses). Above it, the coefficient raised the ceiling by 30% of the excess until 2024, has had no effect since 2025, and **lowers it by 30% of the excess from 2028**.

In completed offices, **85% of projects exceed this threshold**. This is due in particular to the fixed value for the electrical power work package, used by 85% of them, which alone amounts to 115 kgCO2e/m², and to the heating-ventilation value, which amounts to 200 when used. Applied to completed offices, the 2028 Mided would subtract a median of **57 kgCO2e/m² from the ceiling**, more than half the reduction between 2025 and 2028.

> **A priority rule already in place** The ministerial order of 4 August 2021 already requires **preferring specific data**, FDES or PEP, to default data where available; from 2028, the Mided coefficient additionally penalises projects departing from this.

## Which work packages make it possible to meet the 2028 threshold?

In a completed apartment building, average Ic construction of **687 kgCO2e/m²** is distributed across 13 work packages and the construction site. **Superstructure accounts for 21%**, far ahead of other packages, and not all count the same way for compliance.

### Structure: the first lever for the required reduction

In completed apartment buildings, the superstructure package has a median impact of **154 kgCO2e/m²** when the declared structure is concrete, 120 for mixed timber-concrete and **64 for solid timber**. The gap between concrete and timber, 90 kgCO2e/m², alone exceeds **the 70 kgCO2e/m² reduction required in 2028**. It is 53 kgCO2e/m² for detached houses (91 versus 38), against a reduction of 55. For offices, it is 63 (146 versus 83), against a reduction of 100 that must be supplemented by moving away from fixed values.

These comparisons involve modest sample sizes for timber (45 buildings) and a material declared for information in the study, with no effect on the calculation: they give an order of magnitude. A concrete project wanting to pass 2028 without changing its construction system must **optimise quantities and specify [concrete with reduced clinker content](https://projetcelsius.com/en/blog/new-building-carbon-footprint-re2020/)**, documented through [individual FDES](https://projetcelsius.com/en/blog/fdes-vs-epd-vs-pep/).

### Foundations and roads: above a baseline, the threshold adjusts

Adjustments add to the ceiling **the whole excess of the foundations and infrastructure package above 40 kgCO2e/m²**. They do the same for roads and utility networks above 10 (20 for detached houses) and for photovoltaics above 20. An underground car park therefore increases the footprint without jeopardising compliance: **61% of completed apartment buildings** exceed the baseline of 40 and have the excess neutralised.

Reducing a building’s foundations from 120 to 90 kgCO2e/m² therefore does not bring it closer to the threshold, because only the share below 40 counts. The saving remains real for the climate and for [a developer’s scope 3](https://projetcelsius.com/en/blog/scope-3-emissions-guide/), which includes these emissions in its own footprint.

### Technical work packages: moving away from fixed values

The electrical power package uses **fixed values in 83% of completed apartment buildings** (48 kgCO2e/m²), 84% of houses (98) and 85% of offices (115). Replacing them with **PEP declarations for the specified equipment** reduces the share of default data, and therefore the 2028 penalty, and lowers Ic construction as soon as products outperform the fixed value. Our [guide to FDES, PEP and EPD](https://projetcelsius.com/en/blog/epd-fdes-pep-lca-differences/) details what each declaration covers.

### Façades and fit-out: a stable source of impact

Façades, partitions and coverings together account for **190 kgCO2e/m²** in apartment buildings, 28% of Ic construction. Yet the façade package varies little: its median remains **between 58 and 70 kgCO2e/m² depending on the declared insulation**, polystyrenes, mineral wool, wood fibre or cellulose insulation. Savings are achieved product by product, with references covered by individual FDES. These materials’ end of life also falls under the extended producer responsibility (EPR) scheme for construction products, whose [reform is under way](https://projetcelsius.com/en/blog/france-epr-construction-products-pmcb/).

## Where should you start for a permit submitted in 2028?

For a project submitting its permit from 2028, the regulatory calculation is a complete [life cycle assessment](https://projetcelsius.com/en/blog/lca-vs-carbon-footprint/), managed **from outline design**, while structure and heating choices remain open. The stages follow those of an [eco-design process](https://projetcelsius.com/en/blog/eco-design-process-7-steps/) applied to a building.

- **Set the permit submission date**, since the 2025 thresholds apply until 31 December 2027 and the 2028 tier after that, and since gas is excluded from housing from 2027.
- **Calculate against the 2028 threshold from outline design**, including adjustments, keeping a margin for the end-of-works study.
- **Inventory default data and fixed values** work package by work package, and request suppliers’ FDES and PEP before inviting contractors to tender.
- **Decide on structure first**, because it is the work package with the greatest gap between solutions, enough to cover the required reduction for apartment buildings.
- **Check heating**, meaning the network’s carbon content if it is designated and the heat pump’s refrigerant.

For us at Projet Celsius, the costliest mistake is **basing a project on the 2025 threshold because its permit is due to be submitted in late 2027**. A refusal or a programme redesign is enough to push the new submission into 2028, and a structure fixed at outline design is difficult to remedy during execution. Once completed, non-residential buildings of at least 1,000 m² will also come under the [Tertiary Decree (Décret Tertiaire)](https://projetcelsius.com/en/blog/france-tertiary-decree-bacs-obligations/), which will track their actual consumption.

> **What is planned for the 2031 tier?** In 2031, the threshold will fall to **490 kgCO2e/m² for apartment buildings** and 600 for offices. In the observatory, 6% of completed apartment buildings and 12% of offices would already meet it.

## Key takeaways

- **The 2028 tier applies to permits submitted from 1 January 2028**: submission year sets the threshold, regardless of completion date.
- **Ic construction ceilings fall by 10 to 18%**: 580 kgCO2e/m² for apartment buildings, 475 for houses, 710 for offices, 670 to 950 for non-residential uses entering in 2026.
- **Only high-rise buildings obtained a relaxation**, to 95% of the 2025 threshold; no postponement is confirmed as at 28 September 2026.
- **Completed buildings are far from meeting it**: 17% of apartment buildings and 9% of houses would already pass, and default data become a penalty.
- **The reduction is achieved through structure and product data**, with foundations and roads neutralised above a baseline.

For the calculation itself, our [guide to life cycle assessment (LCA) for a new building](https://projetcelsius.com/en/blog/re2020-which-buildings/) describes the study stages. Our article on [choosing between LCA, the Product Environmental Footprint (PEF) and product carbon footprint](https://projetcelsius.com/en/blog/product-carbon-footprint-lca-pef-cfp/) helps manufacturers in the construction sector produce the data their customers will now require.

## Frequently asked questions

### When does RE2020’s 2028 threshold apply?

It applies to building permit applications and prior declarations submitted from 1 January 2028. A permit submitted by 31 December 2027 remains assessed against the 2025 thresholds, regardless of completion date. The next tier will apply to submissions from 1 January 2031.

### What is the 2028 Ic construction threshold for an apartment building?

The average threshold is 580 kgCO2e/m² of habitable floor area, compared with 650 for permits submitted from 2025 to 2027; it will fall to 490 in 2031. The project’s legally binding ceiling is obtained by applying project-specific adjustments. For a residential tower classified as a high-rise building, whose top floor exceeds 50 m, the 2028 threshold is 617.5 kgCO2e/m².

### Does the 2028 threshold apply to non-residential buildings?

Yes: offices fall from 810 to 710 kgCO2e/m² and education from 770 to 680. The 13 uses that entered RE2020 on 1 May 2026 (hotels, shops, restaurants, healthcare, industry, sport, universities…) also face their first tier, a 14 to 18% reduction depending on use. The threshold falls, for example, to 680 kgCO2e/m² for a hotel and to 670 for a shop.

### Has RE2020’s 2028 threshold been postponed?

No: as at 28 September 2026, no legislation postpones the 2028 tier. Decree No 2026-200 of 18 March 2026, issued following RE2020’s evaluation, only relaxed the high-rise threshold, set at 95% of the 2025 value, and added a few adjustments.

### Does an amending permit submitted in 2028 move the project to the 2028 threshold?

In principle no, although the French ministry does not state this explicitly: according to its FAQ No 035, an amending permit requires no new RE2020 certificate, and the updated end-of-works study incorporates project changes. A new permit, submitted after refusal, withdrawal or programme redesign, instead falls under its submission year’s tier.

### Can a gas boiler still be installed in a new home?

No, for housing permits submitted from 1 January 2027. Decree No 2026-863 of 12 September 2026 prohibits every heating, cooling or domestic hot water appliance whose energy emits 79 gCO2e/kWh or more, even for supplementary use. Only district heating connections and emergency equipment remain possible. The ban extends to public buildings in 2028 and to others in 2030.

## Sources

- **Thresholds and adjustments**: French Construction and Housing Code, Articles R. 172-1 and R. 172-4 and [annex to Article R. 172-4](https://www.legifrance.gouv.fr/codes/article_lc/LEGIARTI000054024988), Chapter III (Icconstruction_maxmoyen and Icénergie_maxmoyen values, Miinfra, Mivrd, Mipv, Mided coefficients); [documentation version applicable to permits submitted since 1 July 2026, ministry portal](https://rt-re-batiment.developpement-durable.gouv.fr/textes-en-version-consolidee-a617.html).
- **RE2020 decrees**: Decree No 2021-1004 of 29 July 2021; [Decree No 2026-16 of 15 January 2026](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000053378848) (13 uses on 1 May 2026); [Decree No 2026-200 of 18 March 2026](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000053703809) (high-rise buildings, balconies, ceiling height, air conditioning and designated district heating network); Construction and Housing Code, Article R. 146-3 (definition of high-rise buildings).
- **Calculation method**: Ministerial order of 4 August 2021 on energy and environmental performance requirements for building construction in metropolitan France, Annex II (50-year study period, dynamic method, priority for specific data) and Annex XI (fixed performance values for packages 8, 10 and 11); ministerial order of 19 March 2026.
- **End of gas**: [Decree No 2026-863 of 12 September 2026](https://www.legifrance.gouv.fr/jorf/id/JORFTEXT000054834875), codified in Article R. 172-14 of the Construction and Housing Code; [ministry presentation, 14 September 2026](https://rt-re-batiment.developpement-durable.gouv.fr/fin-du-gaz-dans-la-construction-neuve-a1243.html).
- **Amending permit**: [Ministry RE2020 FAQ No 035](https://rt-re-batiment.developpement-durable.gouv.fr/faq-re2020-035-un-permis-de-construire-modificatif-a610.html).
- **Observatory data**: [OPEE, Observatory of Energy and Environmental Performance of New Buildings, data.gouv.fr](https://www.data.gouv.fr/datasets/opee-observatoire-des-performances-energetiques-et-environnementales-des-batiments-neufs), extract as at 1 January 2026 (completion stage, new construction, 110,906 buildings); [press release from the Ministry for Cities and Housing of 3 September 2026](https://www.ecologie.gouv.fr/presse/ministere-ville-du-logement-rend-publiques-donnees-re2020-accompagner-transition). Projet Celsius processing: 2028 ceiling recalculated from each project’s anticipated 2028 threshold, adjusted to the Mided coefficient applicable in 2028 (excluding adjustments created by Decree No 2026-200). All linked pages are in French.