Skip to content
Database entryHardwareLevel 1 of 6 calculation factorCalculation factor, level 1 of 6Used to calculate 2 entries, level 5Calculated with 1 entry, level 1Database structure

H100 GPU hour, server included

The electricity of one hour of work of an H100 GPU and its share of the server. Projet Celsius estimate.

  • The figure covers the GPU under load and its share of the server's processors, memory, network and fans.
  • The electricity range runs from 700 Wh to 1.3 kWh, within the scope of this entry.
  • CO2e is calculated from electricity and the worldwide grid; it is not a direct measurement of carbon.
  • Out of scope: data centre cooling, counted separately, and hardware manufacturing.
Calculated with
Used to calculate

Origin of the value

Processors, memory, network, fans. The database uses 900 Wh, 70% of the maximum power of the 8-card server given by Nvidia (10.2 kW), the average load used by Epoch AI.

Comparison with the other calculation factors

See the full list
H100 hourthis entry410 gCO2e

Logarithmic axis: each tick is 10 times the previous one.

Characteristics

Unit1 GPU hour
Default locationworld, 458 gCO2e/kWh (Ember 2025, life cycle); 11 other locations to choose from
Countedthe GPU under load and its share of the server's processors, memory, network and fans
Not counteddata centre cooling, counted separately, and hardware manufacturing
Statusestimated, 1 reading with the same scope, 2 other published values
All the characteristics identifier, version, rule for the value, sources, licence
IdentifierIA-0005, projetcelsius.com/en/ai/database/IA-0005/
Version0.1 of 2 November 2026
CategoryCalculation factors, the foundation of the calculation
Choice of the selected valuevalue taken as it stands from its source, without calculation
SourcesEpoch AI, 2025
LicenceCC BY 4.0
Projet Celsius, environmental strategy consultancy

We support companies that account for AI in their Bilan Carbone®