How long does a battery LCA take?

1111 questions from 157 articles available in English.

Allow around 6 months for a first carbon footprint declaration (CFB), plus 4 to 8 weeks of verification by a third-party body. The first month covers scoping and sending supplier questionnaires, months 2 to 4 cover collection, which is the critical path, and month 5 covers modelling and sensitivity analyses. A complete multi-indicator LCA takes 8 to 12 months instead. For a 2nd product with the same value chain, timeframes are roughly divided by 2. To be ready on time, the project must start no later than the second half of 2026.

Read the source article: How do you carry out an industrial battery LCA?