How big will AI's environmental
impact be by 2030, 2035 and 2050?

The data centres that run AI could use almost as much electricity as Japan in 2030 and as much as Russia in 2035, according to the IEA. For 2050, no projection specific to AI exists.

Guillaume Pakula
By Guillaume Pakula, co-founder of Celsius. Since 2019, he has helped 80+ organisations with their Bilan Carbone® and climate strategy.
November 2026
Updated November 2026 · 12 min
By 2030, the electricity used by data centres, driven by AI, would almost double to 945 TWh according to the International Energy Agency, close to Japan's consumption. In 2035, it would stand at around 1,200 TWh, as much as Russia, and up to 1,637 in the highest scenario. The CO2 from this electricity and the water consumed would follow the same slope. For 2050, no serious projection covers AI: the only studies are foresight exercises on digital technology as a whole, built before generative AI.
Key takeaways
  • 1In 2030, the world's data centres would use almost as much electricity as Japan.
  • 2In 2035, the gap between the IEA scenarios is larger than France's entire electricity consumption.
  • 3The CO2 from their electricity would rise from 180 to 320 million tonnes by 2030.
  • 4For 2050, no reference projection exists for AI: only foresight studies of digital technology as a whole.

In 2025, the world's data centres used 485 TWh of electricity (1 TWh, or terawatt-hour, is 1 billion kilowatt-hours), slightly more than the whole of France. Artificial intelligence (AI) has become the main driver of this growth: the consumption of data centres dedicated to it jumped by 50% in a year, according to the April 2026 update from the International Energy Agency (IEA). For 2030 and 2035, the agency publishes 4 scenarios, shown here against the consumption of familiar countries.

IEA projections

Electricity use of the world's data centres, 2024 to 2035

Choose a year: its electricity use is set against that of a country.

05001,0001,500TWh1,637942high scenariolow scenarioFrance, 451Japan, 1,027Russia, 1,1789452024202520302035
2030 · almost Japan

945 TWhin 2030

Japan used 1,027 TWh in 2025. Across the IEA scenarios, 833 to 1,008 TWh.

AI-focused data centres would account for 465 TWh, half of the total.

Sources: IEA, Energy and AI (2025) and Key Questions on Energy and AI (2026, Table A.1); Ember, national electricity demand in 2025; RTE for France.

These figures cover every use of data centres, from cloud storage to video. AI is growing faster than the rest: data centres filled with GPU servers would triple their consumption by 2030. Beyond 2035, no reference projection covers AI.

1How much electricity will AI use?

The IEA publishes the reference series for the world's data centres: scenarios up to 2035, set out in its Energy and AI report of April 2025 and confirmed in April 2026.

In 2030: almost Japan

In the IEA's Base Case, data centres would use 945 TWh in 2030, almost double the 2025 figure. Japan used 1,027 TWh in 2025, according to the annual data from Ember, an energy think tank from which we take our country benchmarks, except for France. The 3 other scenarios frame the Base Case from 833 to 1,008 TWh. These 945 TWh would be about 3% of global electricity, against 1.5% in 2024.

In 2035: as much as Russia, or far more

The agency extends its scenarios to 2035, and itself describes them as exploratory. The Base Case reaches 1,193 TWh, roughly Russia's consumption (1,178 TWh in 2025). The highest scenario, known as Lift-Off, climbs to 1,637 TWh, between Russia and India. The lowest stops at 942 TWh, the level the Base Case already reaches in 2030.

Aerial view of Ashburn, Virginia: dozens of large flat data centre buildings between roads and residential neighbourhoods
Data centres in Ashburn, Virginia, seen from the air. The United States accounted for 45% of the electricity used by the world's data centres in 2024 and would carry the largest share of the increase to 2030, according to the IEA. Photo: Theodore Christopher, Wikimedia Commons, CC0, cropped

And how much of that total is AI alone?

No meter separates AI from other uses. The IEA tracks the data centres it calls AI-focused, which line up GPU servers: they would reach 465 TWh in 2030, half the total, and on their own as much as France (451 TWh in 2025 according to RTE, the French electricity transmission system operator, the benchmark used in all our articles). Other studies go higher. The French collective GreenIT projects 1,169 TWh for AI alone, because it assumes servers running at 69% of their capacity all year round.

Our article on AI electricity consumption compares these studies one by one, and the chart of the 3 projections for 2030 (in French) (in French) puts them side by side. The hub note "AI as much as Japan" (in French) (in French) explains what the comparison measures.

2Why do AI energy projections vary so much?

In 2035, 695 TWh separate the IEA's highest scenario from its lowest, far more than all of France's electricity. The gap comes down to 4 questions nobody can yet answer, and each scenario answers them in its own way.

IEA scenarios

Data centre electricity use under the 4 IEA scenarios

World, in TWh a year: the 2030 value, then the 2035 value, and what each scenario assumes.

Lift-Offstronger adoption, chip and grid constraints lifted
Base Casecurrent trends, constraints included
High Efficiencysame demand, leaner models
HeadwindsAI barely profitable, projects held back

695 TWh gap in 2035, more than the whole of France (451 TWh)

Sources: IEA, Key Questions on Energy and AI, April 2026, Table A.1 (2035 values described as exploratory); RTE, Bilan électrique 2025 (France's annual electricity report).

How many people will use AI, and for what?

In a year, the leading model developers saw their active users triple and their revenue increase fivefold, according to the IEA. Uses are also getting heavier: agents, programs that chain dozens of steps on their own, models that reason before answering and AI-generated video need far more than a written question. The Lift-Off scenario assumes stronger adoption and constraints lifted.

Will models become more efficient?

The High Efficiency scenario assumes the same demand, served by better-sized models and by more computing done on phones and computers themselves. It puts consumption at 1,013 TWh in 2035, 180 less than the Base Case. The gains are real: Google cut the energy of a median Gemini prompt 33-fold in a year, according to its 2026 environmental report. Growing use quickly absorbs them, as our article on the energy of a ChatGPT query shows.

Will the electricity grid keep up?

In 2025, the IEA estimated that around 20% of data centre projects risked delays from an electricity grid already under strain. Lead times for transformers and cables had doubled in 3 years, and gas turbines had to be ordered several years ahead. In 2026, the agency adds a shortage of memory chips for AI, expected to last at least until the end of 2027.

Will the money keep flowing?

Data centres now cost too much to be paid for from companies' own funds alone: they depend on financial markets, and therefore on confidence in AI's profitability. The Headwinds scenario assumes AI that struggles to pay for itself, high interest rates and projects blocked locally. It stops at 942 TWh in 2035. At the other end, the French think tank The Shift Project, which extends announced capacity, sees up to 1,500 TWh as early as 2030, cryptocurrencies included.

3How much CO2, water and waste by 2030?

What electricity emits depends on the power plants that generate it. Data centres also consume water and replace their hardware quickly. For a single building, see our article on the carbon footprint of a data centre.

Beyond electricity

CO2, water and e-waste from data centres to 2030

Choose an impact: its trajectory appears on the object behind it.

The CO2 from the power plants supplying data centres would rise from two thirds of France's emissions to those of the United Kingdom.

Across the IEA scenarios, 215 to about 475 Mt in 2030; about 350 Mt in 2035.

Sources: IEA, Energy and AI (2025) and its 2026 update; Global Carbon Project (2024); Wang et al., Nature Computational Science (2024); Global E-waste Monitor 2024.

CO2: as much as the United Kingdom in 2030

The electricity used by data centres emitted 180 million tonnes of CO2 in 2024, according to the IEA: two thirds of the CO2 emitted by France that year (264 million, according to the Global Carbon Project). In the Base Case, these emissions would reach 320 million tonnes in 2030, as much as the United Kingdom (313 million in 2024). The 2026 update sees them rising further, towards 350 million in 2035. Gas would supply 30% of this electricity in 2030, coal 20%.

These figures count only the CO2 from power plants. GreenIT adds server manufacturing and the other greenhouse gases, for AI alone: 636 million tonnes of CO2 equivalent in 2030, if electricity remains as carbon-intensive as in 2025. That is far more than all of France's greenhouse gas emissions (367 million tonnes of CO2 equivalent in 2024, according to Citepa, the body that compiles France's emissions inventory). Our article on the environmental impact of AI details the method, and the one on AI in a Bilan Carbone® (the French carbon accounting method) brings these totals down to the scale of an SME.

Google's data centre in Eemshaven, the Netherlands, seen from above, surrounded by wind turbines, with industrial facilities on the horizon
Google's data centre in Eemshaven (the Netherlands), in the middle of a wind farm in an industrial port. A data centre's CO2 depends on the power plants that supply it: in 2030, renewables would provide more than a third of the electricity used by the world's data centres, gas 30% and coal 20%, according to the IEA. Photo: Wvdp, Wikimedia Commons, CC0, cropped

Water: more than double between 2023 and 2030

Data centres consume water to cool themselves, and indirectly to produce their electricity and their chips. The IEA estimates this consumed water, meaning water evaporated and not returned to rivers, at 560 billion litres in 2023 and 1,200 billion in 2030. Two thirds came from energy production. In the United States, a large 100-megawatt data centre consumes on average 2 million litres a day, including the water behind its electricity, as much as 6,500 households.

Local conditions matter more than the total: the same litre weighs little in Scandinavia and a lot in Arizona. Our article on the water footprint of AI goes from the drop per question to the whole site.

E-waste: up to 5 million tonnes

A study published in Nature Computational Science in October 2024 estimates that generative AI could produce 1.2 to 5 million tonnes of cumulative e-waste between 2020 and 2030, depending on how fast it develops. That is small against the 62 million tonnes the world discarded in 2022, all devices combined, according to the Global E-waste Monitor 2024. This flow would grow faster if servers were replaced more often or if restrictions on chip imports tightened.

According to the authors, reusing, repairing and recycling data centre equipment would reduce this waste by 16 to 86%. Our article on why AI is bad for the environment shows the weight of manufacturing.

4And in France, what is forecast for 2035?

In France, the projections come from RTE, the electricity transmission system operator, which tracks grid connection requests from data centres. They cover the data centres that host AI, not AI alone.

From 4 or 5 TWh in 2024 to more than 30 in 2035

According to its Bilan prévisionnel 2025 (long-term outlook, in French), data centres located on dedicated sites used 4 to 5 TWh in 2024, less than Luxembourg. RTE retains 2 trajectories, depending on the share of projects that go ahead: 10 to 15 TWh in 2030, then 21 to 32 TWh in 2035. That is between the consumption of Croatia and that of Ireland. A third trajectory considers stagnation, if investment moves to other European countries, if municipalities impose a moratorium or if a financial bubble bursts.

Aerial view of Online's DC3 data centre: a large white building with a row of coloured backup generators along its facade
Online's DC3 data centre (Iliad group) in Vitry-sur-Seine (Val-de-Marne), with its backup generators, seen in 2013. Data centres on dedicated sites in France used 4 to 5 TWh in 2024; RTE expects 21 to 32 in 2035, depending on the share of projects that go ahead. Photo: Online.net / Iliad, Wikimedia Commons, CC BY 3.0

The 32 TWh of the high trajectory would be about 7% of the electricity consumed in France in 2025 (451 TWh according to RTE's Bilan électrique, its annual electricity report, in French). The hub chart on France (in French) (in French) shows the 2 trajectories.

Electricity almost 9 times less carbon-intensive

A kilowatt-hour consumed in France emits 51.9 grams of CO2 equivalent, including power plant manufacturing and losses, according to the Base Carbone of ADEME (the French Agency for Ecological Transition). Worldwide, a kilowatt-hour generated emits 458 on average, according to Ember. Even at 32 TWh, the data centres located in France would emit in the order of 1.7 million tonnes of CO2 equivalent a year, by our calculation. That is less than 0.5% of the 367 million emitted by the country in 2024.

French users also rely on data centres located elsewhere: 53% of their digital uses were hosted abroad in 2022, according to an ADEME study published in 2025. Counting them, the agency estimates that AI accounted for 13% of the electricity used by the data centres serving France in 2025, according to a 2026 study cited by Arcep (the French electronic communications regulator). Our guide to the digital carbon footprint of a company shows how to count these uses hosted elsewhere.

5Can we know what AI will weigh in 2050?

No institution publishes a projection specific to AI beyond 2035, and most stop at 2030. For 2050, the only studies are foresight exercises on digital technology as a whole.

Study horizons

Years covered by published projections

Each bar runs from the last measured figure to the last projected year.

IEA: data centres, world
GreenIT: AI only, world
Shift Project: data centres, world
RTE: data centres, France
ADEME and Arcep: all digital technology in France, before generative AI
AI alone: after 2035
no projection

For 2050, nothing covers AI. The reference foresight study that reaches that far covers all digital technology in France and was built before the rise of generative AI.

Sources: IEA (2025 and 2026), The Shift Project (2025), GreenIT (2026), RTE (Bilan prévisionnel 2025), ADEME and Arcep (2023), Arcep (2026).

What exists: a foresight study of digital technology

The reference foresight study on French digital technology to 2050 is the one by ADEME and Arcep, published in March 2023 (in French). It covers all digital technology: phones, screens, networks and data centres. With no change, its carbon footprint in France would rise from 17.2 million tonnes of CO2 equivalent in 2020 to 49 million in 2050, almost 3 times more. Depending on the model of society chosen, it would range from 9.3 million if sufficiency prevails to 81 million if technology comes first.

This study was built before the rise of generative AI, as Arcep pointed out in May 2026. Its scope was also narrower: ADEME's update, which counts data centres located abroad, already finds 29.5 million tonnes for 2022. France nonetheless plans to stabilise the footprint of digital technology by 2030 to 2035, in its national low-carbon strategy. Our article on digital pollution statistics details these trajectories.

What cannot be said

Nobody knows how many times AI will be used in 2050, how much electricity each use will need, or where that electricity will come from. The IEA itself considers its 2035 figures exploratory, and notes that growth could surprise on the upside after 2030. A figure for AI in 2050 circulating without a scenario or a source would be speculation. Everything will depend on 3 things: the volume of use, the electricity per use and the carbon intensity of that electricity.

At Projet Celsius, we watch the gap between the 2035 scenarios instead: year after year, it will show which way the trajectory is leaning. The signals appear every spring in the IEA and RTE updates: chip deliveries, signed grid connections, and the share of gas in the power plants supplying new sites.

For an organisation, the useful question is closer to home: how much its own use weighs, which is growing faster than models are becoming efficient. That is the subject of our article on the Bilan Carbone® of AI in a company, and our Base IA (in French) (in French) publishes the figures needed to calculate it. The steps that reduce it are in our guide to reducing the environmental impact of AI.

6Key takeaways

  • The world's data centres used 485 TWh in 2025, slightly more than France. The IEA projects 945 in 2030, close to Japan's consumption.
  • In 2035, the IEA scenarios range from 942 to 1,637 TWh, a gap larger than France's consumption.
  • The CO2 from their electricity would rise from 180 to 320 million tonnes in 2030, and the water consumed from 560 to 1,200 billion litres.
  • In France, RTE projects 21 to 32 TWh in 2035 for data centres, with electricity almost 9 times less carbon-intensive than the global average.
  • For 2050, no projection covers AI: the ADEME and Arcep foresight study, which triples the footprint of digital technology, predates generative AI.

To find out which AI uses the least, see our comparison of ChatGPT, Claude and Gemini; for one person's use, our article should you boycott AI?.

Further resources

Frequently asked questions

In the IEA's Base Case (April 2026), the world's data centres would use 945 TWh in 2030, against 485 TWh in 2025, or about 3% of global electricity. AI-focused data centres would account for about half of it, 465 TWh. The agency's other scenarios range from 833 to 1,008 TWh.
Almost, but the comparison covers all data centres, not AI alone. The 945 TWh the IEA projects for them in 2030 approach the 1,027 TWh used by Japan in 2025 (Ember). AI-focused data centres, at 465 TWh, would use roughly as much as France (451 TWh in 2025 according to RTE).
The IEA projects about 320 million tonnes of CO2 in 2030 for the electricity of all data centres, against 180 million in 2024, then about 350 million in 2035. GreenIT, which counts server manufacturing and the other greenhouse gases for AI alone, reaches 636 million tonnes of CO2 equivalent, with electricity unchanged.
About 1,200 billion litres a year according to the IEA, more than double the 560 billion estimated for 2023. This is consumed water, not returned to rivers, two thirds of it linked to energy production in 2023. In the United States, a large 100-megawatt data centre consumes on average 2 million litres a day, as much as 6,500 households.
According to RTE's Bilan prévisionnel 2025, data centres on dedicated sites would use 21 to 32 TWh in 2035, against 4 to 5 TWh in 2024, depending on the share of projects that go ahead. The high trajectory would be about 7% of French electricity. RTE also considers stagnation.
The ADEME and Arcep foresight study (March 2023) projects, with no change, a digital carbon footprint of 49 million tonnes of CO2 equivalent in 2050 in France, almost 3 times that of 2020. Depending on the scenario, it would range from 9.3 to 81 million. This study was built before the rise of generative AI.
or: guillaume@projetcelsius.com

More articles to read

View all →
French environmental cost label for clothing: what changed on 1 October 2026
Regulation

French environmental cost label for clothing: what changed on 1 October 2026

6 min read
What is the French textile eco-score?
Who displays it, and has it become mandatory?
Regulation

What is the French textile eco-score? Who displays it, and has it become mandatory?

12 min read
Removable batteries and battery passports: who is affected in 2027?
Regulation

Removable batteries and battery passports: who is affected in 2027?

14 min read

No two situations are exactly alike.

Tell us about yours: your situation, deadline and budget. A senior consultant will reply within 24 working hours with an honest assessment.

Let us discuss it within 24 hours →
Our toolkit

A full range of free assessment tools

Cost estimator, obligation and eligibility checkers, footprint calculator.

Estimate costs and impacts
Ref. 2026·BC·0184REPORT · FINANCIAL YEAR 2026Bilan Carbone®complete 1·2·3Presentation to the Executive Committee · 2027 action planCONTENTS01Executive summaryp. 402Scope and methodologyp. 1203Emissions by scopep. 24042027 action planp. 5605Methodological appendicesp. 78VOLUME84 pages · ConfidentialSTANDARDISO 14064 · GHG ProtocolQUOTATION · BC.2026.0184Issued 05·05·2026 · Valid for 30 daysCelsius consultancy · Paris 3rd arrondissementINDICATIVE COST ESTIMATEYour companyMid-sized company · 180 employees · CSRD 2027SERVICEBilan Carbone®Scope 1·2·3 · 13 weeksBPIFRANCE FUNDING · - 60%INDICATIVE RANGE EXCL. VAT€16,800to €22,400PROJECT DETAILS01 · SCOPING3 weeks~€4,20002 · MODELLING8 weeks~€9,80003 · PRESENTATION2 weeks~€4,800Indicative estimate · Refined after scopingSIRET 891 234 567 00012

Bilan Carbone® cost estimator

Your price range in 1 minute, based on 2026 market rates and public funding.

1 minStart
Estimate costs and impacts
AI FOOTPRINT · MONTHLY USEYOUR TOTAL FOOTPRINT4.2 kgCO₂eq for 1,000 typical prompts · May 2026MODEL COMPARISON · 1,000 TYPICAL PROMPTSGPT-4oOpenAI6.8 kgClaude OpusAnthropic2.1 kgGemini ProGoogle4.5 kgMistral LargeMistral AI · FR1.6 kg

AI carbon footprint calculator

The climate impact of your AI queries, by model and task. Ecologits methodology.

3 minStart
Check an obligation
DIAGDÉCARBON'ACTIONACCELERATE THETRANSFORMATIONOF YOUR COMPANYIN ENERGY ANDTHE ENVIRONMENTOFFICIAL SCHEME · BPIFRANCE × ADEMECHECKER · ELIGIBILITYELIGIBLEYou meet the 3 Diag Décarbon'Action criteria.YOUR FUNDING€10,000 excl. VAT€6,000excl. VATAmount payable by you after the Bpifrance subsidyFUNDING BREAKDOWNBPIFRANCE 40%YOU 60%€4,000€6,000SCHEME SUBSIDISED BY

Diag Décarbon'Action eligibility

Check in 30 seconds whether your business is eligible for Bpifrance funding covering 40% of a Bilan Carbone® assessment.

30 secStart
Check an obligation
FRENCH REPUBLICMinistry for the Ecological TransitionLEGAL REQUIREMENTGreenhouse GasEmissions AssessmentArticle L.229-25 of the French Environmental CodeDecree 2022-982 · published 1 July 2022FREQUENCY · 4 YEARSFILING · ADEMECHECKER · BEGES REQUIREMENTREQUIRED720 employees · BEGES requirementPOTENTIAL PENALTY€50,000maximum fine for failing to complete itart. R.229-50OFFICIAL REFERENCE

BEGES checker

Does the BEGES requirement apply to you? An immediate answer, with the deadline and penalty.

30 secStart
Check an obligation
9:42SCANSCANNING DPP...DPP IDENTIFIEDOrganic cotton T-shirtSKU TX-CB-220 · Batch L-26-04781ESPR COMPLIANT42 DATA POINTS · 5 SECTIONSORIGINIndia · GOTSOrganic cottonFOOTPRINT5.2 kg CO₂eqLCA ISO 14040RECYCLABILITY85%Cotton recycling schemeREPAIRABILITY7.5 / 10Accessible partsEND OF LIFETextile recycling scheme (TLC) · Bordeaux/FRRefashion-approved recovery operatorEU · ESPR 2024/178112.05.2026

DPP checker

Is your product covered by the Digital Product Passport?

1 minStart
Check an obligation
COSTENVIRONMENTAL386POINTS257PER 100 GOfficial methodEcobalyse, v7.0.0CHECKER · ENVIRONMENTAL LABELLINGELIGIBLETextiles · voluntary labellingENVIRONMENTAL COST386 ptsT-shirt 150 g · 257 pts per 100 gExample: Ministry for the Ecological Transition FAQ

Textile environmental labelling 2026

Voluntary labelling, but third parties can publish it from October 2026: where do you stand?

1 minStart